DO-31724/TE - Assembly and Cabling of Process Control Cabinets
Opening date
January 15, 2019
Closing date
February 15, 2019
Type
Price Inquiry (DO)
Research Facility
CERN
This technical specification concerns the wiring of one pre-series and five series of low tension control cabinets for four LHC cryogenic compressor stations (QSCA).
All the equipment and components will be provided by CERN (except consumable material as listed in § 2.2).
The delivery of the pre-series cabinet is required within eight weeks following notification of the contract, while the remaining five cabinets are required to be delivered in three phases: one batch within three weeks after CERN’sacceptance of the pre-series, the second batch within ten weeks after acceptance of the first batch and the third and last batch within ten weeks after acceptance of the second batch.
För mer information om denna upphandling, kontakta oss.
Första steget att leverera till Cern, anmäl dig i Cerns leverantörsdatabas.