[3602] ID26 lead works

Opening date

July 30, 2025

Closing date

August 29, 2025

Type

Propose suppliers

Research Facility

ESRF

The ESRF is planning to refurbish the ID26 experimental line. This CFT concerns the lead works, including the replacement of a lead wall and the creation of a door in the lead shielding. The dimension of the door should be approx. 0.8m wide and 2m height and 0.09 m thickness, and the wall should be 2m wide, 3m height and 0.02 thickness. the planning : Manufacture until July 2026 for on-site installation October 2026. Note: the manpower part for companies based outside France are subject to French Law on "Temporary posting of workers in France”. (cf. document concerning the temporary posting of workers in France). Note : the technical features installed by the company are subject to French norms, the manpower must have all qualifications required by the french law.