CERN – DO-32058/TE/EPC - Consolidation of two Oil Transformers used for Power Converters 18 kV / 132V, 968 kVA


CERN – DO-32058/TE/EPC - Consolidation of two Oil Transformers used for Power Converters 18 kV / 132V, 968 kVA

This Technical Specification concerns the consolidation of two transformers 18 kV / 132 V, 968 kVA in a specialised contractor’s premises, and the option to consolidate up to two additional transformers of a similar type and power rating. The delivery is foreseen over 18 months from notification of the Contract. The completion of consolidation of the first transformer is expected to take place within 16 weeks from notification of the Contract.